The House Construction.

 
Back

 

 

I have always wanted to live close to my horses and after I had been duly registered in HsinHsu County for the required two years, I applied for a house building permit. Here is a view towards the northeast part of the farm where I planned to build.

2012-04-19

  Here is Lester grazing where the living room will be.

2012-04-21

  Before the construction was started, the building company arranged a ceremony to appease the land gods and ask for protection.

2012-04-23

  The next day the land survey and marking started. We found that a few of the trees were too close to where work was planned and they had to be moved.

2012-04-24

  Finally, on May 1st the excavation started.

2012-05-01

 

As soon as we were a little over 1 meter down, water started to seep in. After all, this is an ancient riverbed I am building on.

2012-05-01

  Looking towards the south from the northern corner of the farm.

2012-05-01

  A quick conference with the construction company when it was discovered that another tree had to be moved. From left: Mr. Lo, me, Mr. Lin and Mr. Wang

2012-05-01

 

  Finally, as sunset approached, the excavation was finished and now we waited for the concrete trucks. A thin layer of concrete was to be laid at the bottom of the pit, to serve as a worksurface for the rebar construction.

2012-05-01

 

  Late at night the concrete had been poured for the 2 inch thick work surface.

2012-05-01

  The surface was now ready for the rebar. Because Taiwan is in an earth quake zone, the rebar work is very important and my father often visited to inspect the quality of the tieing.

2012-05-07

 

  There are tons of rebar in this slab

2012-05-08

  The rebar for the columns are starting to rise up

2012-05-09

  On May 08 I had a follow up meeting with the architect, Archie Kuowey at CYCA Architects.
  Back at the farm, the rebar work for the slab cages continued.

2012-05-08

  I inspected the rebar as often as I could and my father also helped in keeping the quality up.

2012-05-10

  The on-site foreman, Mr. Lo

2012-05-10

  The forms for the slab walls are coming up.

2012-05-12

  Three weeks after the construction started the slab walls are in place.

2012-05-21.

  The compartments in the slab have been filled, concrete has been laid on top and now more rebar and piping jobs are being done.

2012-06-24

  Here are all the conduits for the network, phone and TV-cable coming together in the server room behind the garage.

2012-06-24

  As the brick walls are being built, a cabinet for the communications was put in place.

2012-07-04

  The backside of the living room with the laundry on the right.

2012-07-05

  This is where the kitchen is going to be, looking towards the living room.

2012-07-09

  A view from the front, looking towards the north, just before pouring the concrete for the columns and the 2nd floor.

2012-07-15

  Waiting for the 2nd floor concrete to cure.

2012-08-03

  The 2nd floor concrete has cured and now the 2nd floor walls are being built.

2012-08-11

  Now it is starting to look like a house.

2012-08-14

  The view from the front of the house.

2012-09-02

     
 

 

 

 

Back

Last updated: 2012-09-11 18:36:59 +0800